Granular Road Resurfacing Beginning in June

Granular road resurfacing will be completed throughout the month of June with work taking place Monday to Friday from 7 a.m. to 5:30 p.m.

With a budgeted amount of $439,000, in partnership with Walker Aggregates Inc. and Da-Lee Contracting, 20,000 tons of fresh gravel will be applied to 55.78 kilometres of roads throughout Meaford’s rural areas, along with dust suppressant to help keep dust down.

The road sections included in this project can be found at www.meaford.ca/GranularResurfacing or on the map above.

Please be advised that even the best maintained gravel roads have rough sections and loose gravel that require low speeds. It takes longer to safely stop on gravel roads, and dust can decrease your visibility,” noted the Municipality of Meaford. “Please drive responsibly, take your time, and allow at least six seconds of following distance when driving on gravel roads.”